20th & Brown TID
Status
12/26/06: In
progress
The 20th & Brown Tax Incremental District (TID) was approved in September
2006. The City's Department of Public Works is currently doing design
engineering on the new streets, with construction scheduled to start in
Spring 2007. The developer is planning their marketing strategy and
assembling builders for the project. |
|
 |
27/Center
Status
12/26/06: In progress
Construction started November 27, 2006 and is scheduled for a July 1, 2007
completion. The project includes 24 units and approximately 5,000 square feet of
retail space. |
|
 |
Columbia
Savings & Loan
Status
12/26/06: In progress
This $1.5 million project is constructing a new
10,000 square foot office for Columbia
Savings and Loan. Ground-breaking was in July and
the project is expected to be completed next summer.
Columbia Savings and Loan is
the oldest minority-owned financial institution in the state.
|
|

|
Josey Heights
Status
12/26/06:
In progress
Construction on the porous-paved streets and bioswales was completed
approximately October 31, 2006. The ribbon-cutting ceremony for the new
subdivision was held on November 9. |
|
 |
Toussaint Square
Status
12/26/06:
In progress
Toussaint Square is under construction, with a planned completion of Spring
2007. |
|
|
|
|
|
|